How to Do a Cabinet Takeoff From Construction Plans
In this guide
- What is a takeoff in construction?
- Step 1: Gather the complete plan set
- Step 2: Build a page index
- Step 3: Count room by room, elevation by elevation
- Step 4: Write cabinet line items the shop can build
- Step 5: Countertops
- Step 6: Panels, fillers, scribes and trim
- Step 7: Hardware and accessories
- Step 8: Appliances by others and NIC items
- Step 9: Cross-check plan against elevation
- Step 10: Addenda, RFIs and clarifications
- Step 11: Write exclusions and assumptions
- Quantity takeoff example: a sample cabinet takeoff table
- Traceability: why sheet references matter
- Kitchen cabinet takeoff vs millwork takeoff
- Frequently asked questions
A cabinet takeoff is the list of every cabinet, panel, filler, countertop and accessory in a job, counted from the construction plans, with the type, size, quantity, room and sheet reference for each item. It is the foundation of the bid. If the takeoff is wrong, the price is wrong, no matter how good your shop rates are.
This guide walks through how to do a cabinet takeoff from plans the way experienced estimators do it: collect the full set, index it, count room by room and elevation by elevation, cross-check plans against elevations, and write down your assumptions. At the end there is a sample takeoff table you can copy.
What is a takeoff in construction?
A takeoff (short for quantity takeoff) is the process of measuring and counting the materials and items shown on construction drawings and specifications so they can be priced. Every trade does its own: drywall by square foot, concrete by cubic yard, and cabinets by piece, with sizes, so the shop can price each unit.
A cabinet or millwork takeoff is more detailed than most trade takeoffs because each item has a type, three dimensions, a construction standard and a location. A drywall estimator can live with a total. A cabinet estimator needs to know that the 36-inch sink base in Unit 2B sits on elevation 3 of sheet A-412, because that is what the shop builds, ships and installs.
Step 1: Gather the complete plan set
Do not start counting until you have everything. The most expensive takeoff mistakes come from missing sheets, not miscounts. For a cabinet takeoff from plans, collect:
- Architectural floor plans. Show cabinet locations, room names and overall layout.
- Enlarged plans. Kitchens, baths, break rooms, nurse stations and labs are usually redrawn at a larger scale with cabinet outlines and tags.
- Interior elevations. The most important sheets for casework. They show heights, door and drawer layout, open shelving, appliance openings and countertop edges.
- Details and sections. Show countertop edges, backsplashes, toe kick, scribe, crown, light rail, support brackets and how casework meets walls and ceilings.
- Finish schedule and finish legend. Tell you which plastic laminate, veneer, paint or solid surface goes where.
- Specifications. Division 06 (usually 06 41 00 Architectural Wood Casework, sometimes 06 40 00 Architectural Woodwork or 06 20 00 Finish Carpentry) and Division 12 (12 32 00 Manufactured Wood Casework, 12 35 53 Laboratory Casework, 12 36 00 Countertops). The spec sets the grade, materials, hardware and submittal requirements.
- Addenda and bulletins. Every addendum issued before bid. Read them before you count, not after.
- MEP sheets, where relevant. Plumbing and electrical plans can show sinks, outlets in casework, and equipment that affects cabinet openings.
If you are bidding to a general contractor, ask for the bid form and the scope of work for your package. It often moves items such as countertops, toilet accessories or wood trim in or out of your scope.
Step 2: Build a page index
Before you count, flip through every sheet and write a one-line index: sheet number, title, and whether it has cabinet scope. Note which rooms appear on which enlarged plans and which elevations. Sheet numbering conventions vary by architect, so do not assume; if you need a refresher, see how to read construction drawings.
The index does two jobs. It tells you when you are done, because every sheet with scope gets a check mark. And it gives you the sheet references you will attach to every line of the takeoff.
Step 3: Count room by room, elevation by elevation
Work one room at a time, and inside each room, one elevation at a time. Start at the left end of each elevation and move right. Do not jump around the building looking for "all the base cabinets"; that is how items get counted twice or missed.
For each room:
- Find the room on the floor plan and the enlarged plan. Note the cabinet tags or outlines.
- Go to each interior elevation for that room. Count each cabinet left to right.
- For each cabinet, record type, width, height, depth, quantity and the sheet and elevation number.
- Record panels, fillers, scribes and trim on that elevation before moving to the next one.
- Record the countertop run for that elevation.
- Mark the elevation as done on your page index.
On multifamily, hotel and senior living work, units repeat. Take off each unit type once, carefully, then multiply by the unit count from the unit matrix. Check for mirrored (handed) units and for accessible units, which often have different sink bases, lowered counters or removable base cabinets. Check the 2010 ADA Standards and local code for the actual requirements rather than assuming the architect drew them correctly.
Step 4: Write cabinet line items the shop can build
A useful cabinet takeoff line answers every question the shop and the installer will ask. At minimum, capture:
- Tag or type. Use the architect's tag if there is one (for example, B-3 or WC-2). If there is not, use standard nomenclature such as SB36, DB18 or W3030. See cabinet abbreviations for common codes.
- Width, height and depth. Read dimensions from the elevations and plans. Do not assume standard sizes when the drawings show something else.
- Configuration. Doors, drawers, open, adjustable shelves, false fronts, glass doors, pull-outs.
- Quantity.
- Room or area.
- Sheet reference. Sheet and elevation or detail number, such as 3/A-412.
- Material and finish. From the finish schedule, for example PL-1 or WD-2.
- Notes. Anything unusual: ADA, removable, lock, finished interior, special hardware.
Typical residential sizes are a useful sanity check: most manufacturers build base cabinets about 34-1/2 inches tall and 24 inches deep (36 inches finished with a countertop), and wall cabinets around 12 inches deep in common heights of 30, 36 and 42 inches. Commercial and custom work varies, so treat the drawings as the authority. The standard cabinet sizes chart has more detail.
Step 5: Countertops
Count countertops per elevation as runs, not as one total. For each run record length, depth, material, edge profile, backsplash and sidesplash, cutouts (sink, cooktop, grommets), and any end or waterfall returns. Laminate and solid surface tops are often priced by the linear foot; stone and quartz are usually priced by the square foot from a fabricator.
Check the spec and the bid form to see whether tops are yours. Countertops may sit in 12 36 00, in the casework section, or with a separate trade. If they are excluded, still note the runs so you know what you are coordinating with.
Step 6: Panels, fillers, scribes and trim
These items are small individually and easy to miss, and together they add real material and labor. On each elevation, look for:
- Finished end panels and applied ends
- Dishwasher, refrigerator and island back panels
- Fillers at walls, corners and appliances
- Scribe strips at walls and ceilings
- Toe kick, especially finished or separate toe kick
- Crown, light rail and valances
- Open shelves, floating shelves and support brackets
- Corbels, legs and furniture-style details
If the drawings do not show filler widths, note an allowance and list it as an assumption.
Step 7: Hardware and accessories
The spec usually defines hinges, drawer slides, pulls, locks and shelf supports, and sometimes names a manufacturer and model. Count pulls per door and drawer front, count locks where the drawings or spec require them, and list specialty items such as trash pull-outs, lazy susans, tray dividers, file drawers, keyboard trays and grommets. Commercial specs often require a minimum slide rating or full-extension slides on certain drawers; read the hardware paragraph line by line.
Step 8: Appliances by others and NIC items
Appliances are almost always furnished by others, but the cabinets have to fit them. Record each appliance opening, the appliance model if the drawings give one, and any panel-ready doors or fronts you must supply. Opening widths are set by the specific appliance, so check the cut sheet instead of assuming a nominal size.
Also list items marked NIC (not in contract), OFOI (owner-furnished, owner-installed) and OFCI (owner-furnished, contractor-installed). You do not price NIC items, but writing them down protects you when someone later asks why the refrigerator panel is missing.
Step 9: Cross-check plan against elevation
This is the step that separates a good takeoff from a fast one. For each room:
- Compare the cabinet count and widths on the enlarged plan with the elevations. They should agree. When they do not, note the conflict.
- Add up the cabinet widths and fillers along each elevation and compare the total with the dimensioned wall length.
- Check that every tagged cabinet on the plan appears on an elevation, and every cabinet on an elevation appears on the plan.
- Check that corner cabinets are not counted on both adjacent elevations.
- Confirm the finish codes match the finish schedule.
When plan and elevation disagree, do not quietly pick one. Write an RFI or a clarification, price the more conservative option, and list the assumption on the bid.
Step 10: Addenda, RFIs and clarifications
Read every addendum and mark each change on your takeoff with the addendum number. Addenda often revise a few elevations, change a laminate color, or move scope between trades. If you find a conflict before bid day, submit an RFI through the GC or architect. If there is no time, carry it as a clarification on your proposal.
Step 11: Write exclusions and assumptions
Your takeoff is only as defensible as the assumptions you write next to it. Typical entries:
- Countertops excluded, or included per listed runs only
- Appliances, sinks, faucets and plumbing by others
- In-wall blocking by others
- Filler widths assumed where not dimensioned
- Electrical in casework (outlets, lighting, wiring) by others
- Quantities based on listed sheets and addenda only
These carry straight into your proposal; the cabinet estimate template has a full exclusions list.
Quantity takeoff example: a sample cabinet takeoff table
Here is a short excerpt for a kitchen. The sheet references and tags are illustrative.
| Line | Room | Tag | Description | W x H x D (in) | Qty | Finish | Sheet ref | Notes |
|---|---|---|---|---|---|---|---|---|
| 1 | Kitchen 104 | SB36 | Sink base, 2 doors, false front | 36 x 34.5 x 24 | 1 | PL-1 | 2/A-411 | Plumbing by others |
| 2 | Kitchen 104 | DB18 | Drawer base, 3 drawers | 18 x 34.5 x 24 | 2 | PL-1 | 2/A-411 | Full-extension slides per spec |
| 3 | Kitchen 104 | B15 | Base, 1 door, 1 drawer | 15 x 34.5 x 24 | 1 | PL-1 | 2/A-411 | |
| 4 | Kitchen 104 | DW | Dishwasher opening | 24 opening | 1 | n/a | 2/A-411 | Appliance by others |
| 5 | Kitchen 104 | W3030 | Wall, 2 doors | 30 x 30 x 12 | 2 | PL-1 | 2/A-411 | |
| 6 | Kitchen 104 | U189024 | Tall pantry, 2 doors | 18 x 90 x 24 | 1 | PL-1 | 3/A-411 | 4 adjustable shelves |
| 7 | Kitchen 104 | FEP | Finished end panel | 24 x 34.5 | 1 | PL-1 | 3/A-411 | At range end |
| 8 | Kitchen 104 | F3 | Filler | 3 x 30 | 1 | PL-1 | 2/A-411 | Width assumed, not dimensioned |
| 9 | Kitchen 104 | CT-1 | Solid surface top, 4 in backsplash | 96 x 25 | 1 | SS-1 | 2/A-411, 5/A-520 | Sink cutout |
Every line points back to a sheet. When the GC asks where line 8 came from, or the architect issues a revised elevation, you can find the affected lines in seconds.
Traceability: why sheet references matter
A takeoff without sheet references is a list of numbers you have to trust. A takeoff with sheet references is something anyone in the shop can check. Traceability pays off three times: during your own review, when an addendum changes specific sheets, and after award, when your shop drawings have to match what you bid.
This is also how CabinetHub works: a shop uploads a plan set and receives an estimator-reviewed cabinet takeoff, typically within two business days, where every cabinet carries its type, size, room and sheet reference so the shop can check it against the drawings before pricing it with its own rates.
Kitchen cabinet takeoff vs millwork takeoff
A kitchen cabinet takeoff on residential work is mostly boxes: base, wall, tall, plus fillers, panels and tops. A millwork takeoff on commercial work adds items such as reception desks, wall paneling, window stools, wood base and running trim, often measured in linear or square feet rather than pieces. Commercial casework follows the AWS grade the spec calls for (Economy, Custom or Premium), which affects materials and construction. For the difference in scope, see casework vs millwork.
Frequently asked questions
How long does a cabinet takeoff take?
It depends on the size and quality of the plan set. A single residential kitchen with clear elevations can be done in well under an hour. A multifamily or healthcare project with many unit types, enlarged plans and addenda can take one or more full days, and the cross-checking step should never be skipped to save time.
How do you estimate cabinets from plans?
Gather the full plan set and specs, index the sheets, count cabinets room by room from the enlarged plans and interior elevations, record type, size, quantity and sheet reference for each, add panels, fillers, tops and hardware, then cross-check and price.
What sheets do you need for a cabinet takeoff?
At minimum: floor plans, enlarged plans, interior elevations, casework details and sections, the finish schedule, the Division 06 and Division 12 specifications, and every addendum. Without elevations, sizes and configurations are guesses.
Should I count cabinets from the floor plan or the elevations?
Both. Elevations show heights, configurations and widths most clearly, so count from them. Then check the count against the floor or enlarged plan. Disagreements between the two are common and are exactly what you want to catch before bid day.
What should I do when the plans are unclear?
Submit an RFI if there is time. If not, price the more conservative interpretation, record it as an assumption with the sheet reference, and list it as a clarification on the proposal so the customer knows what you included.