How to Price Custom Cabinets (With a Worked Example)
In this guide
- Cabinet pricing methods
- How to calculate a cabinet shop hourly rate
- What goes into the cost of a cabinet job
- Markup vs margin math
- How to price custom cabinets: a worked kitchen example
- Cabinet installation cost per linear foot
- Cabinet shop profit margin: what to target
- When per-LF pricing breaks
- Common pricing mistakes
- Frequently asked questions
How to price custom cabinets, in one sentence: add up the true cost of the job (materials, hardware, shop labor at a burdened hourly rate, finishing, delivery and installation), make sure overhead is covered once and only once, then divide by one minus your target margin. Per-linear-foot and per-box prices are useful shortcuts, but they should be checked against a cost build-up.
This guide covers the main custom cabinet pricing methods, how to build a burdened shop rate, the markup versus margin math that trips up a lot of shops, a fully worked example, and the mistakes that quietly cost money.
Cabinet pricing methods
There are four common ways to price cabinets. Most shops use one as the primary method and another as a cross-check.
| Method | How it works | Best for | Weak spot |
|---|---|---|---|
| Per linear foot | Price = linear feet of cabinet run x a rate per foot, adjusted by grade or finish | Quick residential budgets and early numbers | Ignores mix of cabinet types, talls, panels and details |
| Per box (unit) | Each cabinet type and size has a price; add panels, fillers and extras | Repeat work with a standard catalog | Needs a well-maintained price list per material and finish |
| Cost-plus / job costing | Materials + labor hours x shop rate + install + delivery, then margin | Custom work, any job worth bidding carefully | Takes longer; only as good as your hours estimate |
| Unit pricing (commercial) | Priced per item, per unit type or per LF of casework to match a bid form | Commercial casework and multifamily | Bid form units may not match how you build |
Cost per linear foot cabinets
Per-linear-foot pricing is the fastest way to give a homeowner or designer a budget. Measure the run of base cabinets and the run of wall cabinets, multiply by a rate, and add for talls, islands and upgrades. Shops define "linear foot" differently: some count base and wall runs separately, some count wall length once for an upper and lower together. Write down which convention you use and use it every time.
The rate itself should come from your own completed jobs. Take the final cost and price of recent work and divide by the linear feet you measured, using the same convention. Do not borrow a number from a forum or a competitor.
Per box pricing
A per-box price list assigns a price to each cabinet type and width in each material and door style. It works well when most jobs use similar construction and you update the list when material costs change. It needs line items for everything that is not a box: panels, fillers, scribes, toe kick, crown, light rail, specialty hardware and inserts.
Cost-plus and job costing
Cost-plus pricing builds the price up from the takeoff. It is the most accurate method for custom work because it reflects the actual mix of cabinets and details on the job. It depends on two things: a good takeoff (see how to do a cabinet takeoff) and a realistic hours estimate per item, which you get from tracking hours on past jobs.
Unit pricing for commercial work
On commercial casework, the GC's bid form may ask for prices per unit type, per room or per item, plus alternates. Price the job by cost build-up first, then distribute the total across the bid form's units. See the commercial casework guide for AWS grades and bid forms.
How to calculate a cabinet shop hourly rate
A burdened shop rate is the hourly cost of producing work in your shop: the labor cost of a productive hour plus the overhead each productive hour has to carry. It is a cost, not a price. Profit goes on top.
The key word is productive. Your people are paid for 40 hours a week, but not all of those hours go into billable jobs. Cleanup, maintenance, rework, meetings, material handling and slow weeks all eat time. Overhead has to be spread across the hours you can actually bill.
Step-by-step burdened rate
- Add up annual shop overhead: rent, utilities, insurance, equipment payments and maintenance, software, vehicles, office and sales salaries, and other costs that are not tied to one job.
- Count paid production hours per year for all shop employees.
- Multiply by your productive percentage, measured from timesheets, to get productive hours.
- Divide overhead by productive hours to get overhead per productive hour.
- Take the average loaded wage: hourly wage plus payroll taxes, workers' comp, benefits and paid time off.
- Divide the loaded wage by the productive percentage to get labor cost per productive hour.
- Add overhead per productive hour and labor cost per productive hour. That is your burdened shop rate.
Example shop rate
Example numbers only. Use your own costs.
| Item | Example value |
|---|---|
| Annual shop overhead | $240,000 |
| Shop employees | 4 |
| Paid hours per employee per year | 2,080 |
| Total paid production hours | 8,320 |
| Productive percentage (from timesheets) | 75% |
| Productive hours | 6,240 |
| Overhead per productive hour ($240,000 / 6,240) | $38.46 |
| Average loaded wage per paid hour (wage plus taxes, comp, benefits) | $32.50 |
| Labor cost per productive hour ($32.50 / 0.75) | $43.33 |
| Burdened shop rate | $81.79 |
Install crews should get their own rate built the same way, with their own wages, vehicle costs and productive percentage. Install hours include drive time, unloading and punch work, so their productive percentage is often different from the shop's.
What goes into the cost of a cabinet job
Build every job price from the same buckets so nothing is forgotten:
- Materials. Sheet goods, solid wood, doors and drawer fronts (made or bought), drawer boxes, edgebanding, finish materials, plus a waste factor for sheet goods.
- Hardware. Hinges, slides, pulls, locks, shelf pins, specialty inserts and organizers.
- Shop labor. Engineering and drawings, cutting, machining, assembly, finishing and packing, in hours x burdened shop rate.
- Outside services. Outsourced finishing, doors, CNC parts, glass.
- Countertops. If included, usually a fabricator quote plus your markup and coordination time.
- Delivery. Truck, fuel and crew hours, and multiple trips if the job site cannot take everything at once.
- Installation. Install hours x install rate, plus fasteners, shims and consumables. On commercial work, also site conditions such as parking, elevators and work-hour restrictions.
- Job-specific costs. Permits, bonds, special insurance, rentals, storage, travel.
Overhead lives in your burdened rate. Do not add it again as a separate line unless you built the rate without it.
Markup vs margin math
This is the most common pricing error in small shops. Markup and margin are not the same number.
- Markup is profit as a percentage of cost.
- Margin is profit as a percentage of price.
To hit a target margin, use price = cost / (1 - margin). To apply a markup, use price = cost x (1 + markup).
| Target | Formula | On $10,000 cost | Price | Profit | Actual margin |
|---|---|---|---|---|---|
| 25% markup | cost x 1.25 | $10,000 x 1.25 | $12,500 | $2,500 | 20.0% |
| 25% margin | cost / 0.75 | $10,000 / 0.75 | $13,333 | $3,333 | 25.0% |
| 33.3% markup | cost x 1.3333 | $10,000 x 1.3333 | $13,333 | $3,333 | 25.0% |
| 30% margin | cost / 0.70 | $10,000 / 0.70 | $14,286 | $4,286 | 30.0% |
Example numbers only. If you think you are earning a 25% margin but you are actually adding 25% to cost, you are earning 20%. On a year of jobs, that gap is large.
How to price custom cabinets: a worked kitchen example
Example numbers only. Every figure below is illustrative; use your own costs, hours and rates.
The job: a custom kitchen with 28 LF of base cabinets, 22 LF of wall cabinets, one tall pantry and an island, painted shaker doors, soft-close hardware. Countertops are by others.
| Line | Basis | Example cost |
|---|---|---|
| Materials (boxes, doors, drawer boxes, finish, sheet waste) | From takeoff and supplier quotes | $6,200.00 |
| Hardware (hinges, slides, pulls, trash pull-out) | From takeoff | $1,450.00 |
| Shop labor | 92 hours x $81.79 | $7,524.68 |
| Installation | 2 installers x 24 hours each = 48 hours x $70.00 install rate | $3,360.00 |
| Delivery | Truck and two people, half day | $350.00 |
| Total cost | $18,884.68 |
Now apply a target margin. Overhead is already inside the shop and install rates, so this margin is profit.
| Step | Calculation | Example result |
|---|---|---|
| Target margin | Shop's choice | 25% |
| Price | $18,884.68 / (1 - 0.25) | $25,179.57 |
| Gross profit | $25,179.57 - $18,884.68 | $6,294.89 |
| Equivalent markup | $6,294.89 / $18,884.68 | 33.3% |
| Check: price per LF of cabinet run | $25,179.57 / 50 LF (base and wall counted separately) | $503.59 per LF |
The last line is the cross-check. Compare the effective per-LF price with your historical per-LF numbers for similar work. If it is far off, find out why before you send the bid: an hours estimate that is too low, a missed panel, or a job that is genuinely different.
Cabinet installation cost per linear foot
Some shops price installation per linear foot of cabinet run, which is fine for budgeting. Build the rate the same way as the cabinet rate: install hours on recent jobs x your install rate, divided by linear feet installed. Then adjust for conditions that change productivity: out-of-plumb walls, upper floors without an elevator, scribing to stone or tile, crown to uneven ceilings, many small rooms instead of one long run. In the example above, installation works out to $3,360 / 50 LF, or $67.20 per LF of cost before margin.
Cabinet shop profit margin: what to target
There is no correct industry margin to copy. Your margin has to cover the risk you take (estimating error, rework, warranty callbacks, slow-paying customers) and fund the shop's growth and equipment. Look at your own job-cost history: compare estimated cost to actual cost on finished jobs, see where you lose money, and set margin targets by job type. It is common to set different targets for small residential jobs, large commercial bids and work with heavy risk such as tight schedules or liquidated damages.
When per-LF pricing breaks
Per-linear-foot pricing assumes the job looks like your average job. It breaks when:
- The mix is unusual: many talls, appliance panels, or lots of drawers instead of doors.
- The run is short. A small vanity or bar has a high cost per foot because setup, delivery and install minimums do not scale down.
- There are details that carry no length: finished island backs, decorative legs, glass doors, lighting channels, specialty inserts.
- Materials or finishes change: exotic veneer, high-gloss paint, inset doors.
- Install conditions are hard: high-rise access, occupied homes, night work.
- On commercial work, items such as reception desks, nurse stations and lab casework rarely fit a per-foot rate.
In those cases, build the price from cost, and treat per-LF only as a sanity check.
Common pricing mistakes
- Using markup when you mean margin. See the table above.
- Pricing labor at wage instead of burdened rate. The wage leaves out taxes, benefits, non-productive time and overhead.
- Counting overhead twice or not at all. Decide whether overhead lives in the rate or in the margin, and stick to it.
- Skipping the small parts. Fillers, scribes, panels, toe kick, crown and specialty hardware add up.
- Not re-pricing materials. Sheet goods and hardware prices change. Refresh supplier pricing for every bid of any size.
- Ignoring delivery and install conditions. Two trips instead of one, or a third-floor walk-up, cost real hours.
- No exclusions. If it is not excluded in writing, the customer may assume it is included. The cabinet estimate template includes a full exclusions list.
- Never comparing estimate to actual. Without job costing, your hours estimates never improve.
CabinetHub is built around this workflow: the shop reviews an estimator-checked takeoff, prices it with its own rates and margin, can pull in supplier quotes, and sends and tracks the bid. The numbers stay the shop's own.
Frequently asked questions
How do you price custom cabinets?
Do a takeoff, estimate materials, hardware, shop hours, installation and delivery, cost labor at a burdened shop rate that includes overhead, then divide total cost by one minus your target margin. Cross-check the result against your historical price per linear foot for similar jobs.
How much should a cabinet shop charge per hour?
Calculate it rather than copying a number. Add your loaded labor cost per productive hour to your overhead per productive hour to get a burdened cost rate, then add profit through your margin. Two shops in the same town can have very different correct rates.
What is the difference between markup and margin?
Markup is profit as a percentage of cost. Margin is profit as a percentage of the selling price. A 25% markup gives a 20% margin. To get a 25% margin, divide cost by 0.75, which is a 33.3% markup.
Is cost per linear foot a good way to price cabinets?
It is good for quick budgets and as a cross-check. It is weak for final pricing on custom or commercial work because it ignores the mix of cabinet types, panels, finishes and install conditions. Build the final price from cost.
Should installation be priced separately from cabinets?
It is usually clearer to show it separately, both for your own costing and for the customer. Build install cost from hours and an install rate, and list site assumptions such as access, wall conditions and blocking in your qualifications.