What to Do When Millwork Plans and Specifications Conflict

Updated · 4 min read

By CabinetHub · Markdown · JSON

In this guide
  1. Describe the conflict before choosing a price
  2. Check the project's own instructions
  3. Use a decision log
  4. Price the exposure separately
  5. Write one answerable question
  6. Carry the answer through the estimate
  7. Related guides
  8. Frequently asked questions

Describe the conflict before choosing a price

A drawing might show a plastic laminate surface while the finish specification names wood veneer. That is a material conflict. An elevation with six doors and a schedule with eight is a quantity conflict. Different countertop thicknesses create another type of discrepancy. Classifying the problem helps you ask for a decision instead of sending a vague request to clarify the entire millwork package.

Create one discrepancy record per decision. Include the room or item, both document references, their issue dates, the contradictory requirements, and the cost or schedule consequence. Keep the record factual. “Elevation 3/A420 identifies finish PL-2; finish schedule lists WV-1 for the same desk” is more useful than “the plans are wrong.”

Check the project's own instructions

Read the invitation, bidding instructions, addenda, scope package, and any applicable contract provisions governing interpretation and questions. Requirements vary. This article proposes an estimating workflow; it does not establish document precedence or determine your contractual obligations.

Confirm who is authorized to answer and the final date for questions. A conversation with a supplier may help quantify exposure but may not be an authorized clarification. Likewise, a general contractor's preliminary interpretation should be recorded as such until the project’s required response process is complete.

Use a decision log

FieldExample entry
Issue IDMW-014
LocationLobby reception desk
ConflictFinish tag differs between elevation and schedule
References3/A420 and finish schedule FS-02
QuestionConfirm finish required for bid pricing
Pricing effectMaterial, finishing, and lead-time change
StatusSubmitted; response pending
Bid basisRecord the chosen basis and qualification

The example is illustrative. Add a responsible person and response due date so an unanswered item does not disappear during the rush to submit.

Price the exposure separately

Before clarification arrives, identify what changes between the plausible interpretations. Do not assume a material substitution is merely the difference in sheet cost. It may affect edge treatment, fabrication steps, finishing, shop drawings, samples, waste, supplier minimums, and delivery timing.

For an illustrative desk, assume option A produces a direct cost of $4,200 and option B $5,050 under your own estimate. The unresolved direct-cost exposure is $850. That number is not a market benchmark or a final alternate price. It identifies the decision's size so the estimator can avoid burying it inside a general contingency.

If permitted by the bid instructions, price a clear base and a separately described alternate. If that format is not permitted, determine the compliant submission approach before relying on a qualification. How to Document Millwork Bid Assumptions and Exclusions discusses precise assumptions and exclusions.

Write one answerable question

A strong request contains the item, contradiction, references, and requested decision. For example: “For reception desk RD-1 in room 101, confirm whether the bid finish is PL-2 shown on 3/A420 or WV-1 listed on FS-02. The selection changes material and finishing scope.” Attach a marked excerpt when allowed. Avoid loading unrelated issues into the same question.

Use How to Write Millwork RFIs Before Submitting Your Bid to structure the request and track its disposition. Set a follow-up before the bid deadline rather than assuming a response will arrive automatically.

Carry the answer through the estimate

When a response arrives, update the takeoff description, rate selection, supplier request, proposal, and revision log. A corrected drawing note is not enough if the estimate still carries the old assembly. Link the response to the affected item IDs and retain the earlier version for comparison.

Before submission, review every open discrepancy. Record whether it was clarified, priced under a stated basis, carried as a permitted alternate, or escalated because the shop cannot responsibly price it. Then save that status with the bid snapshot. How to Track Millwork Quantity Changes Between Drawing Revisions provides a process for comparing quantities and descriptions after an addendum changes the answer.

Frequently asked questions

Do specifications always override drawings?

There is no universal rule to assume for every project. Review the applicable bidding and contract documents and obtain clarification through the stated project process.

What if the clarification arrives after I submit?

Record when it arrived, identify the affected scope and pricing, and follow the project’s procedure for revising or confirming your offer. Preserve the original submitted basis.