{"title":"What to Do When Millwork Plans and Specifications Conflict","description":"Resolve conflicting millwork information with a discrepancy log, focused clarification, explicit bid assumptions, and a documented pricing basis.","answer":"When millwork drawings and specifications conflict, record the exact discrepancy and request clarification through the project’s stated channel. Do not assume a universal rule that one document always wins. Check the bidding instructions and applicable contract documents, then keep the selected pricing basis, unresolved exposure, and any qualifications visible in your proposal.","keyword":"millwork plans specifications conflict","keywords":"millwork plans specifications conflict, millwork document conflicts, bid clarification","category":"scope-review","published":"2026-11-28","updated":"2026-11-28","canonical":"https://www.cabinethub.com/guides/what-to-do-when-millwork-plans-and-specifications-conflict","body":"---\ntitle: 'What to Do When Millwork Plans and Specifications Conflict'\nseotitle: 'When Millwork Plans and Specifications Conflict'\ndescription: 'Resolve conflicting millwork information with a discrepancy log, focused clarification, explicit bid assumptions, and a documented pricing basis.'\nupdated: '2026-11-28'\npublished: '2026-11-28'\nkeyword: 'millwork plans specifications conflict'\nkeywords: 'millwork plans specifications conflict, millwork document conflicts, bid clarification'\ncategory: 'scope-review'\ncategorylabel: 'Scope review and revisions'\nanswer: 'When millwork drawings and specifications conflict, record the exact discrepancy and request clarification through the project’s stated channel. Do not assume a universal rule that one document always wins. Check the bidding instructions and applicable contract documents, then keep the selected pricing basis, unresolved exposure, and any qualifications visible in your proposal.'\n---\n\n> **Quick answer:** When millwork drawings and specifications conflict, record the exact discrepancy and request clarification through the project’s stated channel. Do not assume a universal rule that one document always wins. Check the bidding instructions and applicable contract documents, then keep the selected pricing basis, unresolved exposure, and any qualifications visible in your proposal.\n\n## Describe the conflict before choosing a price\n\nA drawing might show a plastic laminate surface while the finish specification names wood veneer. That is a material conflict. An elevation with six doors and a schedule with eight is a quantity conflict. Different countertop thicknesses create another type of discrepancy. Classifying the problem helps you ask for a decision instead of sending a vague request to clarify the entire millwork package.\n\nCreate one discrepancy record per decision. Include the room or item, both document references, their issue dates, the contradictory requirements, and the cost or schedule consequence. Keep the record factual. “Elevation 3/A420 identifies finish PL-2; finish schedule lists WV-1 for the same desk” is more useful than “the plans are wrong.”\n\n## Check the project's own instructions\n\nRead the invitation, bidding instructions, addenda, scope package, and any applicable contract provisions governing interpretation and questions. Requirements vary. This article proposes an estimating workflow; it does not establish document precedence or determine your contractual obligations.\n\nConfirm who is authorized to answer and the final date for questions. A conversation with a supplier may help quantify exposure but may not be an authorized clarification. Likewise, a general contractor's preliminary interpretation should be recorded as such until the project’s required response process is complete.\n\n## Use a decision log\n\n| Field          | Example entry                                     |\n| -------------- | ------------------------------------------------- |\n| Issue ID       | MW-014                                            |\n| Location       | Lobby reception desk                              |\n| Conflict       | Finish tag differs between elevation and schedule |\n| References     | 3/A420 and finish schedule FS-02                  |\n| Question       | Confirm finish required for bid pricing           |\n| Pricing effect | Material, finishing, and lead-time change         |\n| Status         | Submitted; response pending                       |\n| Bid basis      | Record the chosen basis and qualification         |\n\nThe example is illustrative. Add a responsible person and response due date so an unanswered item does not disappear during the rush to submit.\n\n## Price the exposure separately\n\nBefore clarification arrives, identify what changes between the plausible interpretations. Do not assume a material substitution is merely the difference in sheet cost. It may affect edge treatment, fabrication steps, finishing, shop drawings, samples, waste, supplier minimums, and delivery timing.\n\nFor an illustrative desk, assume option A produces a direct cost of $4,200 and option B $5,050 under your own estimate. The unresolved direct-cost exposure is $850. That number is not a market benchmark or a final alternate price. It identifies the decision's size so the estimator can avoid burying it inside a general contingency.\n\nIf permitted by the bid instructions, price a clear base and a separately described alternate. If that format is not permitted, determine the compliant submission approach before relying on a qualification. [How to Document Millwork Bid Assumptions and Exclusions](/guides/how-to-document-millwork-bid-assumptions-and-exclusions) discusses precise assumptions and exclusions.\n\n## Write one answerable question\n\nA strong request contains the item, contradiction, references, and requested decision. For example: “For reception desk RD-1 in room 101, confirm whether the bid finish is PL-2 shown on 3/A420 or WV-1 listed on FS-02. The selection changes material and finishing scope.” Attach a marked excerpt when allowed. Avoid loading unrelated issues into the same question.\n\nUse [How to Write Millwork RFIs Before Submitting Your Bid](/guides/how-to-write-millwork-rfis-before-submitting-your-bid) to structure the request and track its disposition. Set a follow-up before the bid deadline rather than assuming a response will arrive automatically.\n\n## Carry the answer through the estimate\n\nWhen a response arrives, update the takeoff description, rate selection, supplier request, proposal, and revision log. A corrected drawing note is not enough if the estimate still carries the old assembly. Link the response to the affected item IDs and retain the earlier version for comparison.\n\nBefore submission, review every open discrepancy. Record whether it was clarified, priced under a stated basis, carried as a permitted alternate, or escalated because the shop cannot responsibly price it. Then save that status with the bid snapshot. [How to Track Millwork Quantity Changes Between Drawing Revisions](/guides/how-to-track-millwork-quantity-changes-between-drawing-revisions) provides a process for comparing quantities and descriptions after an addendum changes the answer.\n\n## Related guides\n\n- [How to Document Millwork Bid Assumptions and Exclusions](/guides/how-to-document-millwork-bid-assumptions-and-exclusions)\n- [How to Write Millwork RFIs Before Submitting Your Bid](/guides/how-to-write-millwork-rfis-before-submitting-your-bid)\n- [How to Track Millwork Quantity Changes Between Drawing Revisions](/guides/how-to-track-millwork-quantity-changes-between-drawing-revisions)\n\n## Frequently asked questions\n\n### Do specifications always override drawings?\n\nThere is no universal rule to assume for every project. Review the applicable bidding and contract documents and obtain clarification through the stated project process.\n\n### What if the clarification arrives after I submit?\n\nRecord when it arrived, identify the affected scope and pricing, and follow the project’s procedure for revising or confirming your offer. Preserve the original submitted basis.\n","faqs":[{"question":"Do specifications always override drawings?","answer":"There is no universal rule to assume for every project. Review the applicable bidding and contract documents and obtain clarification through the stated project process."},{"question":"What if the clarification arrives after I submit?","answer":"Record when it arrived, identify the affected scope and pricing, and follow the project’s procedure for revising or confirming your offer. Preserve the original submitted basis."}],"sources":[]}