Scope review and revisions
How to Write Millwork RFIs Before Submitting Your Bid
By CabinetHub · Markdown · JSON
In this guide
- Ask for a decision, not a general explanation
- Use a compact, consistent structure
- A complete sample question
- Separate design questions from scope questions
- Prioritize questions by bid exposure
- Record what the answer actually resolves
- Handle unanswered questions explicitly
- Related guides
- Frequently asked questions
Ask for a decision, not a general explanation
An RFI should reduce a specific uncertainty. “Please clarify millwork” does not tell the recipient what answer you need. “Confirm the finish for reception desk RD-1 because two references identify different materials” defines a decision that can move the estimate forward.
Before writing, check whether the answer already appears in a referenced detail, schedule, specification, addendum, or previous response. Record the sources you checked. That preparation reduces avoidable questions and makes a genuine discrepancy easier to demonstrate.
Use a compact, consistent structure
Include the project, RFI ID, room or item, question, references, and requested response date. Explain the pricing or schedule consequence without asserting an unsupported cost. If you propose an interpretation, label it as proposed rather than treating it as accepted.
| Field | Illustrative entry |
|---|---|
| ID | MW-RFI-007 |
| Location | Room 108, reception desk RD-1 |
| References | Elevation 2/A402; finish schedule FS-01 |
| Issue | Elevation and schedule identify different finishes |
| Requested decision | Confirm finish required for bid pricing |
| Consequence | Material and finishing basis will change |
| Response needed | Before the stated bid clarification cutoff |
Use the project's required form when one is prescribed. Keep attachments focused and readable, with the affected area marked rather than a large unexplained drawing bundle.
A complete sample question
“Reception desk RD-1 in room 108 is tagged PL-3 on elevation 2/A402 and WV-2 in finish schedule FS-01. Please confirm the finish to be used for bid pricing, including exposed transaction surfaces. Our estimate will remain open on this selection pending clarification.”
This is a sample, not a contractual notice or a rule for which reference governs. What to Do When Millwork Plans and Specifications Conflict explains a workflow for conflicting documents. Adjust the wording and submission route to the actual bidding instructions.
Separate design questions from scope questions
A design question asks what must be built: dimension, material, finish, quantity, or detail. A scope question asks who carries a defined activity: supply, field measure, countertop installation, supports, or unloading. Mixing them can yield an answer that resolves only half the problem.
For example, “confirm countertop material and whether we install it” contains two decisions with potentially different respondents. Split them or number them clearly within a coordinated request. How to Separate Casework, Countertop, and Installation Scope provides a responsibility matrix for the commercial boundary.
Prioritize questions by bid exposure
Record which questions block the takeoff, change a major price, or affect supplier lead time. Not every missing note deserves the same urgency. A spelling inconsistency may be harmless; an undefined lobby feature may require a separate supplier and fabrication process.
Set internal due dates before the external cutoff so the estimator has time to apply the response. A late answer can be as disruptive as no answer when it changes the package minutes before submission. Keep a visible list of questions that remain unresolved as the deadline approaches.
Record what the answer actually resolves
When a response arrives, save its reference and date. Link it to the affected item IDs. Update descriptions, quantities, assemblies, supplier requests, and proposal qualifications. If the answer addresses material but leaves the dimension open, close only the material issue.
Do not treat an informal conversation as equivalent to every project's required clarification process. Record its status and obtain the required confirmation where necessary. Contract and procurement obligations depend on the project documents.
Handle unanswered questions explicitly
Review the bid instructions for permitted assumptions, alternatives, and qualifications. State the basis used where appropriate and identify important unresolved exposure. Do not silently choose the cheapest interpretation and assume the question protects the price.
How to Document Millwork Bid Assumptions and Exclusions explains how to document the pricing basis. Finally include the RFI log in the saved bid record so future revisions and project handoff can distinguish confirmed instructions from assumptions that were never answered.
Related guides
- What to Do When Millwork Plans and Specifications Conflict
- How to Separate Casework, Countertop, and Installation Scope
- How to Document Millwork Bid Assumptions and Exclusions
Frequently asked questions
How many questions should one RFI contain?
Keep it focused on one coordinated decision. If different issues can be answered independently or involve different scope owners, separate or clearly number them.
Does submitting an RFI protect an assumption automatically?
No. Follow the project’s instructions and document the actual bid basis. An unanswered question does not by itself establish accepted scope or contract protection.