Free Millwork Addenda Tracking Log
By CabinetHub · Markdown · JSON
In this guide
Free downloads
No signup is required to download these files.
Download the addenda workbook
Download the millwork addenda tracking log. The Excel file includes twenty prepared rows, separate workflow fields, and illustrative examples of a cabinet quantity change and a revised finish selection. Amber cells hold inputs; the calculated workflow-status column shows the earliest incomplete step.
Save the file inside the project’s estimate record. Keep the original received documents, their filenames, and the actual proposal revision separately. The log explains what happened to a change; it is not a replacement for the drawings, specifications, or buyer instructions.
Separate four different events
An update can arrive without anyone reviewing it. It can be reviewed without the estimate being revised. It can be priced without the proposal acknowledgment being completed. Treat those events as distinct:
| Step | Evidence of completion |
|---|---|
| Received | The correct issue was obtained and stored |
| Reviewed | Relevant scope, quantity, material, schedule, and form effects were examined |
| Priced | The estimate reflects the required effect, including a documented no-cost effect |
| Acknowledged | The proposal or buyer process reflects the required acknowledgment |
The workbook progresses through review required, pricing required, acknowledge required, and complete. Mark Yes only when the step is genuinely completed. A change with no price effect still requires a recorded review and disposition rather than being silently ignored.
Record changes at a useful level
Use the addendum identifier, issue date, receipt date, affected sheet or section, and a concise change summary. One broad addendum may contain several materially different millwork changes. Use multiple rows or an associated detail register when one row would hide separate responsibilities.
For example, a revised elevation adding a tall cabinet and a finish schedule changing laminate need different quantity and supplier checks. The same update may also change installation timing or the bid form. Keep the change description specific enough that another estimator can locate the source and understand what needs to happen.
Follow the illustrative cabinet change
The sample EX-ADD-01 identifies an additional tall cabinet on a fictional elevation. Review is marked Yes, pricing No, and acknowledgment No. The status remains “Pricing required.” Updating the quantity register alone does not complete the row if the cost and proposal still reflect the old scope.
After the estimate is updated, mark pricing Yes. The status becomes “Acknowledge required” until the bid’s acknowledgment step is complete. The revision quantity guide explains how to compare old and new quantities without destroying the previous takeoff basis.
Check nonquantity effects
Some important addenda leave cabinet counts unchanged. A material change can alter supplier pricing, fabrication methods, waste, finishing, or lead time. A schedule change can alter crew access, delivery phasing, storage, or overtime assumptions. A form change can alter the requested alternates or price breakdown.
Use the scope checklist to examine those interfaces. Record “reviewed, no cost change” only after checking the applicable consequences. A zero-dollar effect should be an intentional conclusion supported by the scope review, not the default meaning of an empty cell.
Keep multiple buyers synchronized
When several GCs request the same physical project, record which updates each has issued or confirmed. Do not assume that a document received from one buyer automatically establishes another buyer’s current proposal basis. Ask for clarification where the distributions or instructions differ.
Connect the update to the bid tracker and each proposal revision. If the same common takeoff supports several buyers, identify the shared quantity change while preserving buyer-specific scope and submission requirements.
Perform the final bid-day reconciliation
Before submission, compare the log with the buyer’s current document list and the actual proposal. Check that every applicable update has a completed review, a pricing disposition, and any required acknowledgment. Resolve open rows or explicitly handle their effect through the project’s permitted clarification route.
Retain the issued proposal with the estimate revision and the completed log. If another update arrives later, create a new record and identify which issued price it affects. That history makes a revision understandable without relying on memory or an unexplained overwritten total.
Related guides
- Free Millwork Bid Proposal Template
- Free Millwork Scope Checklist for Bid Review
- Free Bid Tracking Spreadsheet for Millwork Shops
- How to Track Millwork Quantity Changes Between Drawing Revisions
Frequently asked questions
Should an addendum with no cost effect still be logged?
Yes, when it is part of the bid basis. Record the review and the conclusion that no quantity, cost, schedule, or proposal change is required.
When does a row become Complete?
When the applicable review, pricing disposition, and acknowledgment steps are recorded Yes. Receipt alone does not complete the workflow.