Skip to content
CabinetHub

Pricing and estimating

How to Price Millwork Delivery, Freight, and Site Handling

Updated · 4 min read

By CabinetHub · Markdown · JSON

In this guide
  1. Define where delivery ends
  2. Build a shipment plan before adding a cost
  3. Work an illustrative logistics estimate
  4. Price the release sequence
  5. Review the physical route
  6. Separate logistics from installation
  7. Make the bid basis usable later
  8. Related guides
  9. Frequently asked questions

Define where delivery ends

“Delivery included” can mean arrival at the site, unloading at a staging area, placement on each floor, or movement into individual rooms. Those are different scopes. Establish the exact boundary in the estimate and make the proposal use the same definition.

Confirm who provides unloading labor, equipment, staging, vertical transport, protection, and installation-area movement. If the shop has not received the site logistics plan, keep the assumption visible and seek the information needed to price the work.

Build a shipment plan before adding a cost

Cost groupDriverInformation to obtain
PackagingProduct and protection needsCrates, pallets, reusable protection
LoadingShipment count and arrangementLabor and equipment responsibility
Freight or truckRoute, load, time, quoted basisService inclusions and limits
UnloadingLoads and site conditionsCrew, equipment, appointment
Site handlingDistance and vertical movementStaging, lifts, access route
Storage or returnsSchedule and release planDuration and extra movements

Use actual quotes or your shop's defined cost basis. This framework does not establish carrier terms, freight classifications, legal obligations, or standard logistics rates.

Work an illustrative logistics estimate

Assume a sample project requires three planned shipments. Each has an illustrative $450 transport cost and four labor-hours of shop loading and site handling that are not included elsewhere. Transport totals $1,350. At an illustrative $40 per labor-hour cost, handling is 3 × 4 × $40 = $480.

Add $300 of separately estimated packaging and the logistics subtotal is $2,130. These are demonstration inputs only. If the carrier or installation quote already includes some handling, remove the duplicated line rather than charging both.

Price the release sequence

A single large shipment and several small phased shipments can carry different loading, transport, staging, and handling costs. Match quantities to buildings, floors, rooms, or release phases. An estimate based on one shipment should not silently become a promise to deliver every time the site requests a few cabinets.

Check whether the site can accept material when fabrication is ready. Off-site storage, repeated rehandling, and delayed delivery can affect both cost and production flow. Record which conditions are confirmed and which remain assumptions.

Review the physical route

Verify the available access information: unloading area, delivery appointment process, opening sizes, elevator or lift arrangements, staging, and travel distance to the work area. These details determine tasks and resources. Do not substitute a blanket “difficult access” percentage for an identifiable handling plan.

If the package includes large custom features, determine whether their intended sections can move through the route. The estimate may need a construction or delivery decision before a reliable handling cost is possible. Escalate that issue rather than assuming the feature can be installed as drawn.

Separate logistics from installation

Some shops carry handling within installation labor; others keep it in logistics. Either can work if the boundary is explicit. How to Estimate Cabinet Installation Labor describes the task-based installation estimate. Reconcile its loading, unloading, and movement assumptions with the freight quotation.

Similarly, packaging may be part of fabrication labor or a project-specific logistics line. Review supplier quotations for delivery and packaging inclusions before adding your own allowance. Free Millwork Supplier Quote Comparison Template helps normalize those differences.

Make the bid basis usable later

State the number or sequence of planned deliveries where relevant, the delivery endpoint, and important access assumptions in a form consistent with the project’s bidding requirements. How to Document Millwork Bid Assumptions and Exclusions provides a structure for specific qualifications.

Save the shipment plan, route information, quotations, handling hours, and responsibilities with the estimate. When the schedule changes, compare the new plan against that basis. A request for an additional phase can then be evaluated as an identifiable logistics change instead of an unexplained increase in the cabinet price.

Frequently asked questions

Does a freight quote include unloading?

Not necessarily. Confirm the quoted service and responsibility boundary. Record unloading, staging, and movement to the installation area separately when they are not included.

Should handling be in installation labor or delivery cost?

Either can work if the scope is clear. Reconcile both estimates so every task appears once and required handling is not omitted.

Get your next takeoff done for you

Upload a plan set and get an estimator-reviewed cabinet takeoff: every cabinet with its type, size, room and sheet reference, traceable to the drawing. Price it with your own rates and send the bid from CabinetHub.

First takeoff: pay only if you're satisfied.

Start my first takeoff